PROJECT PLANNING (CONTD.)
Broad Contents
Life Cycle Phases
Responsibilities of Key Players
Problems in Objective Setting
20.1 Life-Cycle Phases:
To describe it further, project planning takes place at two
levels. The first level is the corporate
cultural approach; the second method is the individual's
approach. The corporate cultural
approach breaks the project down into life-cycle phases, such as
those shown in Table 20.1. The
life-cycle phase approach is
not
an attempt to put handcuffs on the
project manager but to
provide a methodology for uniformity in project planning. Many
companies, including
government agencies, prepare checklists of activities that
should be considered in each phase.
These checklists are for consistency in planning. The project
manager can still exercise his own
planning initiatives within each phase.
Life-Cycle Phase Definitions
In addition to this, the second benefit of life-cycle phases is
control. At the end of each phase
there is a meeting between the project manager, sponsor, senior
management, and even the
customer, to assess the accomplishments of this life-cycle phase
and to get approval for the next
phase. These meetings are often called critical design reviews,
"on-off ramps," and "gates." In
some companies, these meetings are used to firm up budgets and
schedules for the follow-on
phases. In addition to monetary considerations, life-cycle
phases can be used for manpower
deployment and equipment/facility utilization. Some companies go
so far as to prepare project
management policy and procedure manuals where all information is
subdivided according to
life-cycle phasing. Life-cycle phase decision points eliminate
the problem where project
managers do not ask for phase funding, but rather ask for funds
for the whole project before the
true scope of the project is known. Several companies have even
gone so far as to identify the
types of decisions that can be made at each end-of-phase review
meeting. They include:
- Proceed with
the next phase based on an approved funding level
- Proceed to the
next phase but with a new or modified set of objectives
- • Postpone
approval to proceed based on a need for additional information
- • Terminate
project
For instance, consider a company that utilizes the following
life-cycle phases:
-
Conceptualization
- Feasibility
- Preliminary
planning
- Detail planning
- Execution
- Testing and
commissioning
As the name suggests, the conceptualization phase includes
brainstorming and common sense
and involves two critical factors:
1. Identify and define the problem, and
2. Identify and define potential solutions
All ideas are
recorded and none are discarded in a brainstorming session. The brainstorming
session works best if there is no formal authority present and
if the time duration is no more
than thirty to sixty minutes. Sessions over sixty minutes in
length will produce ideas that may
begin to resemble science fiction.
The second phase, that is the feasibility study phase, considers
the technical aspects of the
conceptual alternatives and provides a firmer basis on which to
decide whether to undertake the
project.
Note that the purpose of the feasibility phase is to:
- Plan the
project development and implementation activities.
- Estimate the
probable elapsed time, staffing, and equipment requirements.
- Identify the
probable costs and consequences of investing in the new project.
If practical, the feasibility study results should evaluate the
alternative conceptual solutions
along with associated benefits and costs. The objective of this
step is to provide management
with the predictable results of implementing a specific project
and to provide generalized
project requirements. This, in the form of a feasibility study
report, is used as the basis on which
to decide whether to proceed with the costly requirements,
development, and implementation
phases.
Moving ahead with the life-cycle, the third life-cycle phase is
either preliminary planning or
''defining the requirements." This is the phase where the effort
is officially defined as a project.
In this phase, we should consider the following:
- General scope
of the work
- Objectives and
related background
- Contractor's
tasks
- Contractor
end-item performance requirements
- Reference to
related studies, documentation, and specifications
- Data items
(documentation)
- Support
equipment for contract end-item
-
Customer-furnished property, facilities, equipment, and services
-
Customer-furnished documentation
- Schedule of
performance
- Exhibits,
attachments, and appendices
20.2 Responsibilities of Key Players:
We know that planning simply does not happen by itself.
Companies that have histories of
successful plans also have employees who fully understand their
roles in the planning process. Good
up-front planning may not eliminate the need for changes, but
may reduce the number of changes
required. The responsibilities of the major players are as
follows:
1. Project manager will define:
- Goals and
objectives
- Major
milestones
- Requirements
- Ground rules
and assumptions
- Time, cost, and
performance constraints
- Operating
procedures
- Administrative
policy
- Reporting
requirements
2. Line manager will define:
- Detailed task
descriptions to implement objectives, requirements, and milestones
- Detailed
schedules and manpower allocations to support budget and schedule
- Identification
of areas of risk, uncertainty, and conflict
3. Senior management (project sponsor) will:
- Act as the
negotiator for disagreements between project and line management
- Provide
clarification of critical issues
- Provide
communication link with customer's senior management
Remember that successful planning requires that project, line,
and senior management are in
agreement with the plan.
20.3 Problems in Objective Setting:
It is not possible to satisfy all objectives every time. At this
point, management must prioritize
the objectives as to which are strategic and which are not.
Typical problems with developing
objectives include:
- Project
objectives/goals are not agreeable to all parties.
- Project
objectives are too rigid to accommodate changing
- Insufficient
time exists to define objectives well.
- Objectives are
not adequately quantified.
- Objectives are
not documented well enough.
- Efforts of
client and project personnel are not coordinated.
- Personnel
turnover is high.
|